Dual Penstock Replacement

Owner: Green Mountain Power
Location: Vergennes, VT

The Waterbury Dam

VERGENNES STATION

A challenging undertaking under the best of circumstances, the start date for the project shifted from early summer to mid fall. The two runs of 8.5 foot diameter steel pipe contained square to round transitions, four ring girder supports, four elbows, and connections to the existing turbine pressure cases.  In order to meet the compressed time schedule up to five code certified welders were on the project. Two flux cored wire feed welders were used to boost production while maintaining quality.