Fairbanks MillAbout Fairbanks Mill, Let Us Share Our Experience With You

 

Dam Spillway Reconstruction
LAKE LEVEL CONTROL

Owner: Citizens Utilities
Location: Charleston, VT

Echo Lake Dam

ECHO LAKE DAM

Citizens Utilities was under FERC orders to remediate flow and pond level controls at the Echo Lake Dam, part of the Clyde River Project Relicensing. Under significant time pressures, Citizens hired Fairbanks Mill, Inc. to undertake this project during the brutal late fall and winter season. An elegant system of flow diversion allowed timely resurfacing of the spillway and subsequent reconstruction of the gate structure. Ultimately, this project allowed for ownership of the dam to be transferred from the utility to the State of Vermont.